TL;DR
- Separate internal setup (machine stopped) from external setup (machine running).
- Most shops move 40–60% of setup off the press without buying anything.
- Setup time reduction pays only where the press is the constraint.
Short runs are unprofitable in most shops not because the printing is slow but because a fixed 30-minute setup is spread over 60 garments.
The method
- 1Film the next four setups. You cannot improve what you have not watched.
- 2Classify every action as internal (press must stop) or external (can happen in parallel).
- 3Convert internal to external: pre-registered screens, pre-mixed ink, staged pallets, kitted tools.
- 4Standardise the remaining internal sequence and give it a target time.
- 5Re-measure after two weeks; keep the new time as the costing input.
Setup_cost_per_garment = (Setup_minutes / 60 × Loaded_rate) / Run_size
60-piece job, €28 loaded rate
- Setup 34 min
- €0.26 / garment
- Setup 15 min
- €0.12 / garment
- Saving on 400 such jobs / year
- ≈ €3,400
Interactive example
Registration time released per month
- Hours released
- 10.8 h
- Value if capacity-limited
- € 2.052
- Value if demand-limited
- € 0
Same calculation kernel as the full calculators. For a decision-grade result, open the matching calculator.
Run the numbers in a calculator
Turn your own numbers into a bank-ready PDF report.
Create a reportRelated reading
Improving registration quality and speed
Repeatable registration removes reprints, not just minutes.
7 min14/06/2026
Improving OEE in a print shop
Availability × Performance × Quality — measured on the constraint, not on every machine.
9 min10/06/2026
Typical setup, registration and cycle times
Time benchmarks that decide short-run profitability.
6 min25/06/2026
How to choose between screen printing, DTG and DTF
A decision framework built on run size, colour count, labour and setup — not on brand preference.
10 min14/07/2026